Entrepreneurship Development MCQ || Entrepreneurship Development Questions and Answers Part 1

61. ______  are activities that must be completed immediately prior to the start of another activity.

  1. critical
  2. preceding
  3. succeeding
  4. concurrent

Answer.2. preceding

Explanation:

Predecessor activity – Activities that must be completed immediately prior to the start of another activity are called predecessor activities.

 

62. Activities that cannot be started until one or more other activities are completed but immediately follow are called

  1. critical
  2. preceding
  3. succeeding
  4. concurrent

Answer.3. succeeding

Explanation:

Successor activity: Activity that cannot be started until one or more other activities are completed but immediately succeed them are called successor activity.

 

63. Activities that can be accomplished simultaneously are called ______ activities.

  1. critical
  2. preceding
  3. succeeding
  4. concurrent

Answer.4. concurrent

Explanation:

Concurrent: Activity that can be accomplished simultaneously is known as concurrent activity. An activity can be a predecessor or successor to an event or it may be concurrent with one or more of the other activities.

 

64. _____ is the earliest time an activity can begin.

  1. EFT
  2. LST
  3. LFT
  4. EST

Answer.4. EST

Explanation:

Earliest start time (EST): It is defined as the earliest possible time at which an activity can start. It is calculated by moving from the first to the last event in a network diagram.

 

65. The sum of earliest start time and estimated time to perform the project is called

  1. EFT
  2. LST
  3. LFT
  4. EST

Answer.1. EFT

Explanation:

Earliest start time (EST): It is defined as the earliest possible time at which an activity can start. It is calculated by moving from the first to the last event in a network diagram.

Earliest finish time (EFT): It is the earliest possible time at which an activity can finish.

The relationship between earliest start time, earliest finish time, and duration is given by

Earliest finish time = Earliest start time + duration of that activity

∴ EFT = EST + D

 

66. The latest possible time an activity can finish without delaying the project is called

  1. EFT
  2. LST
  3. LFT
  4. EST

Answer.3. LFT

Explanation:

Latest finish time (LFT): It is the latest possible time at which an activity can finish and still allow the project to be completed on the estimated project completion time.

 

67. Difference between latest finish time and estimated time to perform the project is called

  1. EFT
  2. LST
  3. LFT
  4. EST

Answer.2. LST

Explanation:

Latest start time (LST): It is defined as the latest time an activity can start and still allow the project to be completed on the estimated project completion time.

Latest finish time (LFT): It is the latest possible time at which an activity can finish and still allow the project to be completed on the estimated project completion time.

The relationship between latest start time, latest finish time, and duration is given by,

  • Latest finish time = Latest start time + duration of that activity
  • ∴ LFT = LST + D

 

68. _______ is the difference between the actual sales and break-even sales.

  1. margin of safety
  2. fixed cost
  3. contribution
  4. profit

Answer.1. margin of safety

Explanation:

The margin of safety is the difference between the amount of expected profitability and the break-even point. The margin of safety formula is equal to current sales minus the breakeven point, divided by current sales.

 

69. ______ study is a systematic method adopted to find out the possibility and practicability of starting a project

  1. profitability
  2. liquidity
  3. feasibility
  4. viability

Answer.3. feasibility

Explanation:

A feasibility study sometimes called a feasibility analysis or feasibility report—is a way to evaluate whether or not a project plan could be successful. A feasibility study evaluates the practicality of your project plan in order to judge whether or not you’re able to move forward with the project.

 

70. Which of the following is not a phase in the project life cycle?

  1. pre-investment phase
  2. construction phase
  3. normalization phase
  4. growth phase

Answer.4. growth phase

Explanation:

The Project Life Cycle is divided into three-phase

  1. The Pre-investment Phase
  2. The Construction Phase
  3. The Normalisation Phase

Pre-investment or pre-contract expenditures may generally be defined as costs incurred in preparatory work for the making of the investment.

The construction phase is the physical process of building and all other associated activities such as landscaping, refurbishing, site clearance, and demolition.

Normalization aims at eliminating anomalies in data. The process of normalization involves three stages, each stage generating a table in normal form.

 

71.  Which of the following is a technique of project identification?

  1. desk research
  2. sensitivity analysis
  3. cvp analysis
  4. none of these

Answer.1. desk research

Explanation:

Project managers can use several tools to identify risks in a project. They include documentation reviews, information gathering, brainstorming, checklist analysis, assumption analysis, diagramming, SWOT analysis, desk research and expert judgment techniques.

Desk research is basically involved collecting data from existing resources hence it is often considered a low-cost technique as compared to field research, as the main cost is involved in executive’s time, telephone charges, and directories.

 

72.  Decision regarding factory design is part of

  1. network analysis
  2. financial analysis
  3. technical analysis
  4. social cost-benefit analysis

Answer.3. technical analysis

Explanation:

Technical evaluation has the most important place in the evaluation of a new or proposed project which is done by qualified and experienced experts in the field. If the project size is very big and is of technical importance then the service of experts from outside can also be taken. The decision regarding factory design is part of technical analysis.

 

73. Which of the following is not a network technique?

  1. CPM
  2. PERT
  3. SWOT
  4. LOB

Answer.3. SWOT

Explanation:

The term project networks analysis is a generic term covering all the network techniques used for planning, scheduling, and controlling projects. The three commonly used techniques are The critical Path Method (CPM), Program Evaluation and Review Technique (PERT), and Precedence Network Analysis (PNA).

SWOT is a part of Marketing management.

 

74.  Shortest possible time to complete an activity is _______

  1. pessimistic time
  2. optimistic time
  3. most likely time
  4. none of these

Answer.2. optimistic time

Explanation:

An optimistic Time Estimate is a shortest possible time for completing an activity if everything proceeds as planned without any problem i.e. the activity is performed under ideal conditions.

 

75.  Maximum possible time to complete an activity is _______

  1. pessimistic time
  2. optimistic time
  3. most likely time
  4. none of these

Answer.1. pessimistic time

Explanation:

A pessimistic Time Estimate is a maximum time required to complete an activity under abnormal or extremely adverse conditions in which everything goes wrong. The estimate, however, does not include catastrophes such as fires, earthquakes, floods, etc.

Scroll to Top